The Manxman won’t be back in service by the end of November as originally scheduled, the Isle of Man Steam Packet Company has confirmed,
The vessel is now due to return to service on December 11 – subject to the delivery of remaining parts, reassembly, regulatory inspection and sea trials.
Meanwhile, Lloyd’s Register is carrying out an independent investigation into the cause of the original wear on bearings that led to the lengthy lay-off.
During installation of the vessel’s new bearings last week, it became apparent that the existing locking arrangement no longer met the “fine tolerances” required to secure them correctly.
New tapered locking wedges are now being manufactured.
Once the parts have been delivered, the remaining steps are reassembly, regulatory inspection and sea trials.
Return Date
The company will confirm the return to service date once the parts have been delivered and will “advise immediately” should there be any further change.
Any passenger whose booking is affected will be contacted directly by the Steam Packet reservations team from today, in travel-date order, and assisted with alternative arrangements.
Managing director Brian Thomsson said: “Firstly, I would like to apologise to all affected customers for the inconvenience caused by this further delay.
“Although this is not the outcome we had hoped to announce today, it’s important that we complete this work to the highest standard before Manxman returns to service.”
He added: “We know this extension will be frustrating for affected customers, and our teams are focused on completing the work safely and efficiently while supporting passengers whose travel plans may be affected.
“The cause of the original wear is being investigated independently by Lloyd’s Register, and we will provide an update on their findings once that work is complete.”