According to the Manx Development Corporation (MDC) the construction works on the former Nurses’ Home are proceeding at pace and on budget.
The full refurbishment of the building will provide 37 contemporary one and two bedroomed apartments, and a coffee and patisserie facility.
The project is currently on programme to be completed in early 2025.
Former Nurses’ Home
Extensive investigations during the design phase demonstrated the poor condition of the building, identifying asbestos and water ingress as significant challenges.
MDC says it is managing these issues through sympathetic remediation and remodelling, in keeping with the original design of the structure.
The first phase of the construction works, which included the total strip-out of much of the internal fabric and the demolition of the unsalvageable original fourth floor, is now complete.

The new fourth floor is being rebuilt in complimentary brick and new glazing has been installed, up-to and including the third floor.
Substantial installation of internal partitions is well underway, as is the first-fix of mechanical & electrical.
MDC say it is very encouraged by the progress of its maiden on-site project, and looks forward to providing further updates on this exciting restoration, as it brings this former landmark back to life.