MUA Planning Reservoir Sun Farm

Manx Utilities is exploring the feasibility of solar panels floating on the surface of Sulby Reservoir.

Chairman John Wannenburgh MHK revealed the plans in Keys this morning.

Mr Wannenrburgh was asked for an update on plans for solar panels on publicly owned building by Jason Moorhouse.

This follows the government announcing in July 2023 that 30 sites, including the NSC, Noble’s Hospital and the Sea Terminal – had been identified as suitable for solar installations.

Solar

Responding to Mr Moorhouse, the chairman confirmed that while the rooftop scheme at the NSC remained the priority, other options were being reviewed.

“Manx utilities also has considered other options for delivering solar across the public estate,” he said, adding, “Manx utilities is reviewing the potential for a floating solar scheme on Selby reservoir.

“This review includes a capacity assessment and crucially any potential impact on water quality and our essential water stock.”

Initial feasibility work has also taken place for a ground-mounted solar installation at a site in the north of the island, with surveys for both projects planned for this year.

Ditched?

Tim Glover also queried the status of two other locations previously highlighted. “Have they now been ditched?” he asked, referring to Noble’s Hospital and the Sea Terminal building.

The chairman told members: “I believe they have been suspended for the time being.”

The session revealed significant delays to the original programme.

Lawrie Hooper expressed disappointment, noting that according to earlier timelines, customers should already be benefiting from solar power at the NSC, Noble’s and the Sea Terminal by 2024.

Mr Wannenburgh acknowledged the slippage, adding: “Certainly we are behind where we should be or where we said we would start.

“”There have been some difficulties with rooftops that were not known at the time, so we have had to conduct further surveys to ensure that they are suitable sites.

“Absolutely. I agree with the honourable member. We are not where we want it to be, but we are certainly progressing as quickly as we can and as thoroughly as we can.”

Mr Wannenburgh also said the works are likely to cost £800,000, less than the £1m initially projected for this financial year.